TxDOT Weekly Road Work Report
The Texas Department of Transportation releases their Weekly Road Work Report for May 20-26.
Bowie County
US 259 – At Red River north of De Kalb, constructing new bridge.
US 259 – From US 82 to FM 44, adding shoulders.
FM 1297 – From FM 2878 to FM 559, widening highway.
Camp County
None
Cass County
None
Harrison County
I-20 Westbound – From SH 43 near Marshall to Gregg County Line, upgrading bridge railing.
I-20 – From FM 31 to US 80, repairing pavement.
FM 2625 – From SH 43 to 0.5 mile west, constructing mine haul road overpass.
FM 134 – From SH 43 to FM 1999, seal coating highway.
FM 450 – From I-20 to FM 968, seal coating highway.
Marion County
None
Morris County
None
Panola County
SH 149 – At SH 315, constructing overpass and widening highway.
SH 149 – From Rusk County Line to FM 124, resurfacing highway.
SH 43 – From FM 959 to Rusk County Line, resurfacing highway.
FM 699 – From FM 2517 to Shelby County Line, seal coating highway.
FM 31 – From FM 123 to 5.1 miles south of FM 2517, seal coating highway.
Titus County
US 271 – From end of freeway section of US 271 to 0.3 mile south of FM 3417, extending freeway lanes and constructing overpass at FM 3417.
US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.
Upshur County
SH 155 – From south of Sabine River to US 80, replacing bridges and widening roadway.
SH 155 – From FM 1002 to US 259, upgrading guard rail.
FM 1650 – From SH 154 to Gregg County Line, seal coating highway.